Buying data center space

How to plan a move into a data center

Moving into a data center is a project, not a moving day. The provider delivers space on its schedule, and the risk of the move is yours. Here's the plan.

Realistic timelines: plan back from your go-live date#

  • Racks and cages: 30 to 90 days from signing to live.
  • A megawatt or more, or a custom build: 6 to 24 months.

Need to be live in under 30 days? Most options are already off the table. The move itself comes after the space is ready, so add it on top.

What to settle before you sign#

A move plan that starts after signing is already behind. Start from what you need, then add two things:

  • An equipment list with size and weight, not just power. Rack layout, floor loading and delivery all depend on it.
  • A map of what depends on what. It tells you which systems move alone, which move together, and which must stay up.

What has to be ready before your gear arrives#

Power tested, connections live, and access sorted. That means circuits, carrier lines and cross-connects, badges and delivery times.

Run both sites, or cut over in one go? Run both#

A single cutover has no way back if something breaks. Running both sites keeps the old one live until the new one proves itself under real load.

Running both costs money, because you pay twice during the overlap. A failed cutover with nothing to fall back on costs a lot more. Run both unless the workload can really go down.

What the overlap needs to prove#

  • It works under real load, not just switched on.
  • Your data matches on both sides, including anything written during the overlap.
  • You can roll back. Rehearse it before you need it.
  • You've set the go and no-go signals ahead of time, not in the moment.

How Clectiv AI solves this#

Doing this on your own means months of chasing reps, one at a time. Every call starts from scratch, and every provider knows they're the only one in the room.

With Clectiv AI, it's days, not months. Tell us about your project once, and it goes to every provider that fits, at the same time. They know they're competing, so their best numbers come back side by side.

You start where others finished, with 20+ years of buyer-side deals and our own data on 2,200+ buildings behind your request.

Get early access →

Cutover, and shutting down the old site#

If the overlap did its job, cutover is the boring part. Pick a quiet window and run the rehearsed plan. Keep the old site ready until the new one has run clean for a period you set in advance.

Check your old contract's exit terms before you pick a leaving date. What your contract should include shows what to look for.

Common questions#

How long does a move into a data center take?#
Plan on 30 to 90 days from signing to live for racks and cages, or 6 to 24 months for a megawatt or more. The move itself comes after that. Order carrier lines early, because they're often the longest wait.
What is a parallel run in a data center migration?#
Running your old and new sites at the same time, and only moving traffic once the new one proves itself. It costs more, but you keep a way back if something breaks.
Should I do a single cutover or run both sites?#
Run both for anything where downtime or lost data hurts. A single cutover is fine for workloads that can really go down. Decide system by system, before you plan the move.
Is there a platform that speeds up choosing a data center before a move?#
Clectiv AI sends your project and go-live date to every provider that fits at once. You find out who can hit your date and sign in days, not months.